SUNY-Geneseo/Physics & Astronomy
Fall 2002
Experimental Physics
(Phys 364)
Th 2:00pm, Greene 232
 
Dr. Pogo  (pogo@geneseo.edu)                                 Pogo's Home Page
        Office: Greene 232
        Phone: 245-5287
        Office Hours:         Mon/Tue 1:30 - 3:30; W 3:30-5:00

What am I doing here? Hopefully, you are here because you asked to be here. All students in this course must have a faculty sponsor before they can register. This course (sometimes called “Senior Lab”) is designed to introduce you to research techniques in experimental physics. Each student is expected to undertake a project which requires originality and broadens your knowledge.
There is no book for this course, and there are no exams.
 
 
How will I be graded? Your grade will be determined by:
Abstract 5%
Scope of Work 10%
Weekly Assignments 25%
Final Report/Presentation 20%
Sponsor Evaluation 40%
clip art of microscope

The abstract is due on Thursday, August 29, 2002 . The abstract should be a ½ page summary of the project motivation and goals. The abstract should indicate the names and contact information for any external sponsor or supervisors for your project. This abstract will be used by the Physics Faculty as the basis for approval to continue with the project.

 The Scope of Work is due on Thursday, September 12, 2001 . The Scope of Work should define your project. It should have sections describing the motivation of the project, the goals of the project, and the activities you think are necessary to reach the goal. It should also include, in calendar form, an estimated timeline for these steps. This timeline should be very detailed, and should include major tasks and all subtasks (a Gantt chart; see reverse side of this syllabus). You should indicate which steps, if any, are dependent on the completion of other steps before they can be begun.

 Each week, you will be required to submit a short progress report (hardcopy) including the following:

1.       A list of the activities actually completed during the previous week. For each activity, you must include the amount of time spent (to the nearest ½ hour) on it (and by whom, if you are part of a group). Activities might include communicating with sponsors, examining product catalogs or contacting vendors, performing analysis, creating circuit diagrams, etc.

2.       For efforts that have been unsuccessful, indicate an alternative plan of attack for your future work. It is OK if you fall behind the schedule you establish in the Scope of Work; but, for each such activity, you must write a paragraph detailing the reasons that you are behind schedule, as well as how you plan to catch up by the end of the semester.

3.       Revisions to the scope of work or the timeline (as necessary).

4.       A short summary or transcript of communications made with any external sponsor during the previous week (includes personal conversations, telephone calls, email, etc.). Each item should be dated.

5.       A list of activities that you hope to complete during the following week, including an estimate of how much time (to the nearest 1 hour) each activity will require.

 Each project will require a final presentation (given to the physics faculty, at a minimum) or a final report. The final report is intended to document how the goals of the project have been met. The requirements of the final report will vary depending on the needs of your project sponsor.

 
 
The partial Gantt chart below is provided as an example. Note that only the first 3 tasks are appropriately sub-tasked. Your chart will, of course, vary greatly from this one.

example of Gantt Chart